How we connected operations and finance
Kugghuset brought accounting data from Fortnox and work orders and time from SevenTime together in a data warehouse. Power BI then retrieved data for project analysis, customer analysis and the income statement. The finance team could track project results alongside the work performed.
- Fortnox
- Posted revenue and costs
- SevenTime
- Work orders and reported time
- Power BI
- Project analysis from the data warehouse
Three reconciliations using synthetic figures
Project P-101 is fictitious. The amounts, counts and times below are example data showing how the checks work.
1. Did the data arrive from the source systems?
Compare the identifiers for the same project and period in the source systems and the data warehouse. In the example, journal entry V-042 is missing after the first import from Fortnox. All work orders and time entries from SevenTime have arrived.
| Dataset | Source | Warehouse before | Warehouse after |
|---|---|---|---|
| Journal entries in Fortnox | 42 | 41 | 42 |
| Work orders in SevenTime | 12 | 12 | 12 |
| Time entries in SevenTime | 18 | 18 | 18 |
Once the missing journal entry has been imported, the identifiers in the example match. A successful job and matching row counts are useful signals. Comparing identifiers shows which records actually arrived.
2. Do the project amounts reconcile with Fortnox?
Reconcile the revenue and cost accounts against an accounting extract from Fortnox for the same company, project and accounting period. In the example, V-042 contains a materials cost of SEK 3 500. The missing amount made the project result appear SEK 3 500 better.
| Item | Fortnox | Warehouse before | Warehouse after |
|---|---|---|---|
| Revenue | 125 000 | 125 000 | 125 000 |
| Materials and purchases | 28 500 | 25 000 | 28 500 |
| Other costs | 49 500 | 49 500 | 49 500 |
| Project result | 47 000 | 50 500 | 47 000 |
The project result here is posted revenue minus posted costs. The 186 hours reported in SevenTime are displayed as a separate measure.
3. Did Power BI read the new reporting data?
The Power BI refresh at 08.00 succeeded and read the data prepared at 07.00. The data warehouse did not build the corrected data until 08.20. Compare the version actually held in the model and trace an amount all the way to the report.
| Check | Data warehouse | BI 08.00 | BI 08.30 |
|---|---|---|---|
| Dataset built | 08.20 | 07.00 | 08.20 |
| Journal entries | 42 | 41 | 42 |
| Project result | SEK 47 000 | SEK 50 500 | SEK 47 000 |
At the next refresh at 08.30, the model shows the correct version, the correct number of journal entries and a project result of SEK 47 000. The check applies to the version and project result that were compared.
What could be verified in the client project
- The company used the project analysis in its performance reviews.
- In a documented reconciliation, all reviewed income statement accounts matched the Fortnox accounting records to the öre.
- A separate check showed matching row counts in Power BI and the data warehouse for all reviewed reporting tables.